ΩOhmReady

Sizing a Subpanel for a Workshop: Load Inventory, Feeder Calculation, and Breaker Selection

Sizing a subpanel for a workshop or detached garage is not a matter of picking a round number and hoping it works. The NEC requires a load calculation that accounts for every circuit you plan to install, applies the correct demand factors, and then sizes the feeder conductors and overcurrent protection to match. Get it wrong, and you either end up with a subpanel that trips under normal use or one that costs hundreds more than necessary.

This guide walks through the complete process for sizing a subpanel for a workshop or garage—from building a load inventory through feeder conductor selection with voltage drop verification.

Step 1: Build the Load Inventory

Before you can size anything, you need to know what the subpanel will feed. List every circuit with its load in VA (volt-amperes) or amps. For a typical detached workshop, the inventory looks something like this:

Circuit Load Continuous? Notes
General lighting (400 sq ft × 3 VA/sq ft)1,200 VAYesNEC 220.12 (or 120.12 in 2026 NEC)
General-purpose receptacles (2 circuits)3,000 VANo1,500 VA per circuit per NEC 220.14(J)
Table saw (15A, 240V)3,600 VANoNameplate or FLA × voltage
Air compressor (20A, 240V)4,800 VANoMotor load—use nameplate FLA
Welder receptacle (50A, 240V)12,000 VANoDedicated circuit
Dust collector (12A, 120V)1,440 VANoMotor load
Garage door opener600 VANoTypically < 6A at 120V
EV charger (Level 2, 40A, 240V)9,600 VAYesNEC 625—treated as continuous load
Total connected load36,240 VA
NEC Reference The 2026 NEC reduced general lighting load from 3 VA/sq ft to 2 VA/sq ft for dwelling units (Article 120.12). If your AHJ has adopted the 2026 NEC, use 2 VA/sq ft for the workshop if it is part of a dwelling unit. Detached workshops classified as non-dwelling may still use 3 VA/sq ft per the commercial lighting table. Confirm with your local AHJ.

Step 2: Apply NEC Demand Factors

You do not size the subpanel for the full connected load because not everything runs simultaneously. The NEC provides demand factors that reduce the calculated load to reflect realistic usage patterns.

For a workshop subpanel that is part of a residential service, you can apply the NEC 220.82/120.82 optional method for the overall service calculation, but the feeder to the subpanel is typically calculated using standard Article 220 demand factors:

  • General lighting and receptacles: first 3,000 VA at 100%, remainder at 35% per NEC Table 220.42
  • Fixed appliances (4 or more): 75% demand factor per NEC 220.53
  • Motor loads: largest motor at 125% per NEC 430.24
  • EV charger: continuous load, so the conductor must be sized at 125% of the load current per NEC 210.20(A)
Worked Example: Workshop Load Calculation

Lighting and receptacles: 1,200 + 3,000 = 4,200 VA

  • First 3,000 VA at 100% = 3,000 VA
  • Remaining 1,200 VA at 35% = 420 VA
  • Subtotal: 3,420 VA

Equipment loads: 3,600 + 4,800 + 12,000 + 1,440 + 600 = 22,440 VA

With 5 fixed appliances, apply 75% demand factor: 22,440 × 0.75 = 16,830 VA

Add 25% of largest motor (air compressor at 4,800 VA): 4,800 × 0.25 = 1,200 VA

EV charger (continuous): 9,600 VA (no demand factor reduction for a single EVSE)

Total calculated demand: 3,420 + 16,830 + 1,200 + 9,600 = 31,050 VA

At 240V single-phase: 31,050 / 240 = 129.4A

Step 3: Select the Subpanel Size

The calculated demand of 129.4A means you need at least a 150A subpanel (next standard size up). A 100A panel would be undersized. A 200A panel provides room for future expansion but requires larger (and more expensive) feeder conductors.

Consider these factors when choosing between 150A and 200A:

  • Future loads: if you anticipate adding a second EV charger, battery storage, or additional power tools, size up to 200A now—running a new feeder later costs far more than oversizing the initial installation
  • Main panel capacity: verify the main panel has enough spare capacity to feed the subpanel. A 200A main service feeding a 150A subpanel with a full house load may require a service load calculation to confirm capacity.
  • Circuit spaces: a 150A panel typically has 30–42 spaces; a 200A panel has 40–42 spaces. For a workshop with 8–12 circuits, either provides adequate room.

Step 4: Size the Feeder Conductors

The feeder from the main panel to the subpanel must be sized for the calculated load. For a 150A subpanel with 129.4A calculated demand:

Conductor Material Minimum Size (75°C) Ampacity
Copper (THWN-2)1/0 AWG150A
Aluminum (THWN-2)3/0 AWG155A

For a cost-effective installation, many contractors choose aluminum for subpanel feeders of this size. A 3/0 aluminum feeder costs significantly less per foot than 1/0 copper while providing equivalent ampacity.

Step 5: Check Voltage Drop on the Feeder

This is the step that separates a code-minimum installation from a reliable one. For a detached workshop, the feeder run is often 75–150 feet or more. NEC 215.2(A) Informational Note recommends keeping feeder voltage drop at or below 3%, with the total (feeder plus branch circuit) at or below 5%.

$$V_D = \frac{2 \times K \times I \times L}{CM}$$
Worked Example: Voltage Drop Check

150A subpanel, 130A calculated load, 100-foot run, 240V single-phase.

3/0 aluminum (167,800 CM):

$$V_D = \frac{2 \times 21.2 \times 130 \times 100}{167{,}800} = \frac{551{,}200}{167{,}800} = 3.28\text{V} = 1.37\%$$

Well within the 3% recommendation. Even at 150 feet:

$$V_D = \frac{2 \times 21.2 \times 130 \times 150}{167{,}800} = \frac{826{,}800}{167{,}800} = 4.93\text{V} = 2.05\%$$

Still under 3%. At 200 feet, however:

$$V_D = \frac{2 \times 21.2 \times 130 \times 200}{167{,}800} = \frac{1{,}102{,}400}{167{,}800} = 6.57\text{V} = 2.74\%$$

Approaching the limit. For runs beyond 200 feet, consider upsizing to 4/0 aluminum (211,600 CM) or running a detailed voltage drop calculation at the actual expected load rather than the calculated demand.

Step 6: Size the Overcurrent Protection

The feeder breaker in the main panel must not exceed the ampacity of the feeder conductors. For 3/0 aluminum at 155A (75°C column), the next standard breaker size down that does not exceed the conductor ampacity is 150A. Per NEC 240.4(B), you may use the next standard size up only when the conductor ampacity does not match a standard breaker rating—155A is not a standard size, so a 150A breaker works.

Common Mistake Installing a 200A breaker on conductors rated for 155A. The breaker protects the conductor, not the panel. If you want a 200A subpanel for future expansion, you must install feeder conductors with at least 200A ampacity (4/0 copper or 250 kcmil aluminum at 75°C).

Step 7: Four-Wire Feeder and Grounding

A subpanel in a detached structure requires a four-wire feeder: two hots, a neutral, and an equipment grounding conductor (EGC). Per NEC 250.32(B), the neutral and ground must be kept separate at the subpanel—no neutral-ground bond in the sub. Remove the bonding screw or strap in the subpanel.

Size the EGC per NEC Table 250.122 based on the feeder overcurrent device:

Feeder Breaker Copper EGC Aluminum EGC
60A10 AWG8 AWG
100A8 AWG6 AWG
150A6 AWG4 AWG
200A6 AWG4 AWG

For a detached structure, NEC 250.32(A) also requires a grounding electrode system at the workshop (typically a ground rod or concrete-encased electrode). This is in addition to the EGC in the feeder.

Quick-Reference: Workshop Subpanel Sizing Summary

Workshop Type Typical Demand Panel Size Feeder (Al) Feeder (Cu)
Light use (lighting + receptacles + small tools)30–50A60A4 AWG Al6 AWG Cu
Medium use (+ table saw, compressor, welder)80–120A100–125A1/0 AWG Al3 AWG Cu
Heavy use (+ EV charger, multiple 240V circuits)120–160A150–200A3/0–4/0 AWG Al1/0–2/0 AWG Cu
Full shop (commercial-level equipment)160–200A+200A250 kcmil Al4/0 AWG Cu
Tip Always verify your feeder sizing accounts for both ampacity and voltage drop. On short runs (under 50 feet), ampacity is usually the controlling factor. On long runs to a detached workshop (100+ feet), voltage drop often forces you to upsize beyond the minimum ampacity requirement. Use a wire size calculator that checks both constraints simultaneously.

Permit Checklist

Before pulling wire, most AHJs require a permit application with:

  • Load calculation worksheet showing all circuits and demand factors applied
  • Feeder conductor size, type, and installation method
  • Subpanel rating and number of spaces
  • Grounding electrode system for the detached structure
  • Conductor sizing justification referencing NEC table numbers

An inspector will verify that the installed feeder matches the permitted load calculation. Showing up with a 100A subpanel when the load calculation demands 150A means pulling wire twice.